RACI matrix
A RACI matrix is a grid of tasks against people. It states who is Responsible, Accountable, Consulted and Informed for each task, and it answers: who does what, and who has the final say?
Also called: responsibility assignment matrix.
| Letter | Role | Meaning |
|---|---|---|
| R | Responsible | Does the work |
| A | Accountable | Owns the result and signs it off. One person only |
| C | Consulted | Gives input before the work is done |
| I | Informed | Is told once the decision is made |
When to use it
- A project involves several people or an outside partner, and roles have not been spelled out.
- Work falls between two people, or gets done twice.
- Decisions stall because nobody is sure who makes them.
How to do it
List the tasks and decisions
Write ten to twenty-five rows, each starting with a verb: choose the platform, approve the budget, train the team. Include the decisions, not only the work.
List the people or roles
Put them across the top. Use roles when several people share one, and names when the team is small.
Assign the letters
For each task ask four questions. Who does it? Who answers for the result? Whose input is needed first? Who needs to know afterwards?
Check each row
Every task needs exactly one A and at least one R. Keep the C entries few: each one adds a conversation before the work can move.
Check each column
A person with many R entries may be overloaded. A person with many A entries may become the point where everything waits. A person with no letters may not need to be on the project.
Agree it with the team
Walk through the grid together. The disagreements are the value of the exercise: each one is a confusion found before it cost time.
Example: a retailer launching an online store
A shop with one owner, a marketing lead and an operations lead hires a web agency to build its online store. Five tasks are enough to show how the grid reads.
| Task | Owner | Marketing lead | Operations lead | Web agency |
|---|---|---|---|---|
| Choose the platform | A | C | C | R |
| Write the product pages | I | A, R | C | I |
| Set up payments and shipping | I | I | A, R | C |
| Build and test the site | I | A | C | R |
| Approve the launch | A | R | R | I |
Every task has one person accountable. The owner signs off two decisions, the platform and the launch, and is informed on the rest, so the project does not wait on one desk. The marketing lead carries the most letters, with two tasks to answer for and two to work on. That column is the one to watch for overload, and the first place to move work if the timeline slips.
Common mistakes
- Giving one task two A entries. When two people answer for a result, nobody does, so choose one.
- Consulting everyone. Mark as C only the people whose input changes the work, and inform the rest.
- Mixing up R and A. The R does the work and the A answers for the result. On a small team one person can hold both, so write both letters.
- Building it alone and filing it. The grid works only when the people in it have agreed to it.