RACI matrix

A RACI matrix is a grid of tasks against people. It states who is Responsible, Accountable, Consulted and Informed for each task, and it answers: who does what, and who has the final say?

Also called: responsibility assignment matrix.

LetterRoleMeaning
RResponsibleDoes the work
AAccountableOwns the result and signs it off. One person only
CConsultedGives input before the work is done
IInformedIs told once the decision is made

When to use it

  • A project involves several people or an outside partner, and roles have not been spelled out.
  • Work falls between two people, or gets done twice.
  • Decisions stall because nobody is sure who makes them.

How to do it

  1. List the tasks and decisions

    Write ten to twenty-five rows, each starting with a verb: choose the platform, approve the budget, train the team. Include the decisions, not only the work.

  2. List the people or roles

    Put them across the top. Use roles when several people share one, and names when the team is small.

  3. Assign the letters

    For each task ask four questions. Who does it? Who answers for the result? Whose input is needed first? Who needs to know afterwards?

  4. Check each row

    Every task needs exactly one A and at least one R. Keep the C entries few: each one adds a conversation before the work can move.

  5. Check each column

    A person with many R entries may be overloaded. A person with many A entries may become the point where everything waits. A person with no letters may not need to be on the project.

  6. Agree it with the team

    Walk through the grid together. The disagreements are the value of the exercise: each one is a confusion found before it cost time.

Example: a retailer launching an online store

A shop with one owner, a marketing lead and an operations lead hires a web agency to build its online store. Five tasks are enough to show how the grid reads.

TaskOwnerMarketing leadOperations leadWeb agency
Choose the platformACCR
Write the product pagesIA, RCI
Set up payments and shippingIIA, RC
Build and test the siteIACR
Approve the launchARRI

Every task has one person accountable. The owner signs off two decisions, the platform and the launch, and is informed on the rest, so the project does not wait on one desk. The marketing lead carries the most letters, with two tasks to answer for and two to work on. That column is the one to watch for overload, and the first place to move work if the timeline slips.

Common mistakes

  • Giving one task two A entries. When two people answer for a result, nobody does, so choose one.
  • Consulting everyone. Mark as C only the people whose input changes the work, and inform the rest.
  • Mixing up R and A. The R does the work and the A answers for the result. On a small team one person can hold both, so write both letters.
  • Building it alone and filing it. The grid works only when the people in it have agreed to it.