Capacity planning
Capacity planning compares the hours your team has with the hours your work needs, week by week. It answers the question: can you deliver what you have promised, and can you take on more?
Also called: resource capacity planning.
Utilization = allocated hours ÷ available hours
- Available hours: contracted hours × focus share × (1 - days off ÷ 5)
- Focus share: the part of the week left for project work after meetings, admin and support
- Allocated hours: the hours planned on projects in that week
When to use it
- A new project or client is on the table and you want to know whether the team has room.
- Some people are stretched while others have time, and you want to see it in numbers.
- Deadlines slip and you want to find out which projects are short of hours.
How to do it
List people and their hours
For each person, note the contracted hours per week and a focus share. Start with about 70% and adjust it for each role.
Subtract time off
Enter holidays and other days off for each week. A person with one day off has four fifths of the usual hours.
List projects with dates and effort
Give each project a start week, an end week and an estimate of the total hours it needs.
Allocate hours
Plan how many hours a week each person spends on each project while it runs.
Read utilization
Divide allocated hours by available hours for each person and each week. Above 100% is overload. Well below it, for example under 60%, is spare time.
Check each project
Compare the hours planned on a project with its estimate. A shortfall means the project needs more people, more time or less scope.
Example: one week for a team of three
Ana and Ben work 40 hours a week with a focus share of 70%. Cleo works 30 hours with a focus share of 80%. Ben has one day off this week.
| Person | Available hours | Allocated hours | Utilization | Status |
|---|---|---|---|---|
| Ana | 28.0 | 30 | 107% | Over |
| Ben | 22.4 | 20 | 89% | OK |
| Cleo | 24.0 | 12 | 50% | Spare |
| Team | 74.4 | 62 | 83% | OK |
The team as a whole has room: 83% of its available hours are planned. But Ana is over her limit while Cleo has 12 hours free. Moving a few hours of work from Ana to Cleo fixes the week with no new hire. The team figure alone would have hidden this, which is why the reading is done person by person and week by week. The same check applies to projects: a project that needs 240 hours over six weeks, with 30 hours a week planned, gets 180 hours and is short by 60.
Common mistakes
- Planning on contracted hours. Fix: plan on focus hours, after meetings and admin.
- Looking only at the team average. Fix: read each person, week by week.
- Forgetting holidays. Fix: enter time off before you allocate.
- Filling everyone to 100%. Fix: leave room for the unexpected.