MoSCoW prioritization
MoSCoW prioritization sorts a list of requirements into four groups: Must have, Should have, Could have and Will not have this time. It answers: with fixed time and budget, what do we deliver first and what do we leave out?
Also called: MoSCoW method.
| Group | Meaning | Test |
|---|---|---|
| Must have | Without it the project fails | Would we cancel the launch without it? |
| Should have | Important, but a workaround exists | Painful to leave out, not fatal |
| Could have | Wanted, with little effect if left out | The first to go when time runs short |
| Will not have this time | Agreed as out of scope for now | Written down, so it is not reopened |
When to use it
- The list of things you want from a project is larger than the budget or the deadline allows.
- Several people each call their own request essential.
- You are scoping the first version of a product, a website or a new system.
How to do it
Fix the frame
State the deadline, the budget and what counts as finished. Without a fixed frame nothing forces a choice, and everything stays a Must have.
List every requirement
Write one line each, with an estimate of the effort in hours or days. Rough estimates are enough.
Sort with the people affected
Apply the test for each group, starting with the Must haves. Ask what would happen if the item were missing on launch day.
Check the load
Add up the effort per group. A common guide from agile practice keeps Must haves to about 60% of the total, which leaves room when work overruns.
Deliver in order and review
Build the Must haves first, then the Should haves. When the plan changes, sort again and do not simply add to the list.
Example: a physiotherapy clinic building a new website
The clinic has a budget of 200 hours with its web developer. Seven requirements are on the list.
| Requirement | Hours | Group |
|---|---|---|
| Online booking | 60 | Must have |
| Service and price pages | 40 | Must have |
| Layout that works on phones | 20 | Must have |
| Patient intake form | 30 | Should have |
| Team profiles with photos | 20 | Should have |
| Blog | 20 | Could have |
| Exercise video library | 60 | Will not have this time |
The Must haves total 120 hours, which is 60% of the budget. The Should haves bring the plan to 170 hours and the blog to 190, leaving 10 hours spare. The video library would take the total to 250, so it is recorded as out of scope for this version. If the booking system overruns, the blog is the first item to go, and everyone knows that in advance.
Common mistakes
- Calling everything a Must have. Apply the test strictly: if a workaround exists, the item is a Should have.
- Leaving out the last group. Write down what will not be delivered this time, or the same requests return every week.
- Sorting without estimates. A Must have list that exceeds the budget is not a plan, so add up the effort.
- Sorting alone. The people who will use the result should take part, or they will not accept the order.
Dai Clegg created the method in 1994, and it became a core practice of the DSDM agile framework.