Guides / Finance

Net present value

Net present value (NPV) is the value today of all the cash a project brings in, minus all the cash it costs. It answers the question: does this investment create value once the timing of the money is counted?

Also called: NPV.

NPV = CF0 + CF1 ÷ (1 + r) + CF2 ÷ (1 + r)^2 + ... + CFn ÷ (1 + r)^n

  • CF0: the cash flow today, usually the investment, entered as a negative number
  • CF1 to CFn: the net cash flow of each later year
  • r: the discount rate, the yearly return you require
  • n: the number of years

When to use it

  • An investment costs money now and pays back over several years.
  • You are comparing projects of different size or timing.
  • You want one figure that shows the value a project adds.

How to do it

  1. Estimate the cash flows

    For each year, take the cash coming in and subtract the cash going out. Year 0 holds the investment you pay at the start.

  2. Choose a discount rate

    Use the return you could earn elsewhere at similar risk, or your cost of borrowing plus a margin. A riskier project calls for a higher rate.

  3. Discount each year

    Divide each cash flow by (1 + r) raised to the number of the year. The result is its present value: what that future amount is worth today.

  4. Add them up

    The sum of all present values, including year 0, is the NPV.

  5. Read the sign

    Above zero, the project earns more than your required return. Below zero, it earns less. Between two projects of similar risk, the higher NPV adds more value.

Example: a new packing machine

A machine costs 50,000 today and should bring in 15,000 of net cash a year for five years. The discount rate is 10%.

YearCash flowDiscount factorPresent value
0-50,0001.0000-50,000
115,0000.909113,636
215,0000.826412,397
315,0000.751311,270
415,0000.683010,245
515,0000.62099,314
NPV6,862

The machine brings in 75,000 in total, but those future amounts are worth 56,862 today. After the 50,000 investment, the NPV is 6,862. The project earns the required 10% and adds value on top. At a rate of 15%, the NPV of the same project falls to 282, close to zero. The answer depends on the rate, so set the rate with care.

Common mistakes

  • Mixing profit and cash. Fix: use cash in and cash out, and leave out depreciation.
  • Picking a discount rate to get the answer you want. Fix: set the rate before you run the numbers, and use the same rate across similar projects.
  • Forgetting running costs or the cash tied up in stock. Fix: list every cash effect of the project.
  • Reading NPV alone. Fix: check the payback period and a cautious scenario as well.

Irving Fisher set out the present value approach to investment in The Rate of Interest (1907) and The Theory of Interest (1930).