Payback period
The payback period is the time an investment takes to earn back what it cost. It answers the question: how long is the money at risk?
Payback = full years before recovery + (amount still to recover ÷ cash flow of the recovery year)
- Full years before recovery: the last year in which the running total is still below zero
- Amount still to recover: that running total, taken as a positive number
- Even cash flows: the formula becomes investment ÷ yearly cash flow
When to use it
- Cash is tight and you want to know when an investment stops being a drain.
- You want a quick first screen before a fuller analysis.
- The further future is hard to forecast, so early returns matter most.
How to do it
List the cash flows by year
Year 0 holds the investment as a negative number. Each later year holds the net cash the project brings in: cash in minus cash out.
Build a running total
Add each year to the total so far. The total starts below zero and climbs as the project pays back.
Find the recovery year
It is the first year in which the running total reaches zero or more. The investment is recovered at some point during that year.
Work out the fraction
Divide the amount still to recover at the start of that year by the cash flow of that year. Add the result to the full years before it.
Compare with your limit
Set the longest payback you accept, for example three years, before you calculate. A payback at or under the limit passes. Choose a shorter limit for riskier projects, where the later years are harder to count on.
Example: new kitchen equipment
A café spends 24,000 on equipment. It expects extra net cash of 8,000 in year 1, 10,000 in year 2 and 12,000 in year 3.
| Year | Cash flow | Running total |
|---|---|---|
| 0 | -24,000 | -24,000 |
| 1 | 8,000 | -16,000 |
| 2 | 10,000 | -6,000 |
| 3 | 12,000 | 6,000 |
The running total turns positive during year 3. At the start of that year 6,000 is still to recover, and the year brings in 12,000, so the fraction is 0.5. The payback period is 2.5 years, inside a limit of three years. The measure says nothing about year 4 and beyond. Two projects with the same payback can differ widely in what they earn afterwards, which is why payback works best beside a measure of total value.
Common mistakes
- Ignoring what happens after payback. A project that pays back fast can still earn little. Fix: read the net present value beside it.
- Using profit in place of cash. Fix: count cash in and cash out.
- Treating a late year like an early one on long projects. Fix: also check the discounted figures.
- Setting no limit in advance. Fix: decide your longest acceptable payback first.